A well-run dry-docking is planned a year ahead. The cost of a docking is driven far more by what is found and added during the work than by the yard's base prices — so the work spent on the specification is the best money saved.

12–9 months before

  • Check the class status: special survey, intermediate survey and bottom survey windows (cargo ships normally need two inspections of the outside of the bottom in each five-year period), tail-shaft survey, overdue recommendations.
  • Check statutory certificates that fall due around the docking.
  • Set the budget and the target period; agree it with the commercial team (off-hire days).

9–6 months before

  • Build the specification: standard docking items, hull and coating, sea valves, propeller and rudder, plus the due PMS jobs, open defects and class items that need a dock.
  • Ask the crew for their list; the Chief Engineer and Master know what has been put off.
  • Order long-lead spares and owner's supplies.

6–3 months before

  • Send the specification to three or more yards. Ask for a price per item, dock days, the daily dock and berth charge, and the rates for extras.
  • Compare quotes item by item, not just the total: a cheap total with items left unpriced is not cheap. Include deviation costs and off-hire days.
  • Award, agree the contract terms and the dates.

The last month

  • Confirm the docking plan, gas-free arrangements, crew changes and attending superintendents, maker engineers and the class surveyor.
  • Prepare tanks, spares and the list of photos and measurements to take.

During the docking

  • Daily progress meeting and log. Record every extra (variation order) with its price before it starts.
  • Track progress and cost against the budget every day; close class items with the surveyor as they are done.

After

  • Check the final invoice item by item against the agreed prices and extras.
  • Update the PMS history, certificates and the IHM for anything replaced.
  • Write a short report: what went well, what to change next time.
This guide summarises the rules for day-to-day use. For a survey, an audit or a legal question, check the official text of the convention or regulation, your flag Administration's instructions and your classification society.